Leith Walk / Elm Row indicative tramworks end date published

10 Oct 2022

The Trams to Newhaven project have just published their updated completion dates down Leith Walk.

From North to South:

Kirkgate to Crown Street: December 2022

Crown Street to Manderston Street: November 2022

Manderston Street to Montgomery Street: November 2022

Elm Row: January 2023 (due to landscaping works)

Picardy Place: November 2022

Once construction finishes, snagging and testing will take place until March 2023 when the line will go live.

Full details are available at Point 7.4 of the following PDF: https://cl-assets.public-i.tv/.../Full_Meeting_Papers...

This website uses cookies

Like most websites, this site uses cookies. Some are required to make it work, while others are used for statistical or marketing purposes. If you choose not to allow cookies some features may not be available, such as content from other websites. Please read our Cookie Policy for more information.

Essential cookies enable basic functions and are necessary for the website to function properly.
Statistics cookies collect information anonymously. This information helps us to understand how our visitors use our website.
Marketing cookies are used by third parties or publishers to display personalized advertisements. They do this by tracking visitors across websites.