Electric Charging Points Update


A number of questions have been asked, about when the newly-installed on-street electric vehicle charging points will be operational.

Please see the table below for the latest information that I have been given on this topic.

  

Location Charger Install Grid Connection Testing and Commissioning
Ingliston Park & Ride Complete Complete Complete
King's Road Complete Complete 04/07/22
Fettes Avenue Complete Complete 04/07/22
Montgomery Street Complete Complete 11/07/22
Comely Bank Complete Early July Late July
Thirlestane Road Complete Early July Late July
East London Street Complete Early July Late July
Sheriff Brae Complete Early July Late July
Heriot Row Complete Early July Late July
Maxwell Street Complete Early July Late July
Stewart Terrace Complete Early July Late July
Hermiston Park & Ride Complete Complete 04/07/22 (delayed by sickness)

 


Share this post on social media:

Sign in with Facebook, Twitter or Email.